Waiver of Right to Assess Liquidated Damages

By Christopher Solop



Contractors who have a liquidated damage provision in their contracts should be aware that their assessment can be waived by the conduct of the owner.  The Mississippi Supreme Court has found that an owner was estopped from asserting delay damages where it failed to timely assert that right.  Contractors faced with a liquidated damage provision may therefore be able to defend against assessment of these damages where the owner fails to affirmatively and timely assert the right to them.  This may occur when the owner waits until the end of the project, long after the completion date has passed, to claim its right to liquidated damages without deducting them as they accrue.